Annual Development Plan for the year 2007-2008

 
   
Sr.No.
UC #
Name of Scheme
Estimated
Cost in Rs.
Progress
Payment Rs.
Progress
Physical Rs.
Union Council
1
31
Carpeting of link Aslam Chowk remaining portion U.C 31
214000
207961
100%
Completed
2
32
Construction of PCC Baba Bari Wala remaining portion U.C 32
500000
497500
100%
Completed
3
131
Construction of road remaining portion Jinnah Road Pindi Raj Pottan U.C 131
500000
500000
100%
Completed
4
128
Construction of road remaining portion D-Block Faisal Town Lahore U.C 128
150000
149250
100%
Completed
5
127
Construction of PCC Q-Block Flat Model Town Extension
700000
690058
100%
Completed
6
95
Construction of road Rana Shaukat Mahmood road to Park G- Block Gulberg Lahore
3600000
2650000
75%
W.I.P
7
95
Repair road near junior model school Main Market Gulberg Lahore
205000
205000
100%
Completed
8
95
Construction of road near Shehzan Bakery Main Market Gulberg Lahore
800000
704266
100%
Completed
9
32
Construction of PCC Streets Masjid Pathana Wali U.C 32
540000
540000
100%
Completed
10
129
Construction of PCC Ali Street Liaqatabad Kot Lak Pat
400000
354565
100%
Completed
11
126
Improvement of main road Aibak Block Garden Town near National Bank remaining portion
400000
352005
100%
Completed
12
76
Carpeting of Hassan Din Street sewing School to Ghari Shahu Chowk U.C 76
1000000
924500
100%
Completed
13
76
Construction of PCC Al Qadri Marriage Hall Street U.C 76
750000
530000
100%
Completed
14
76
PCC behind Police Station Ghari Shahu Assembly Quarters U.C 76
700000
501490
100%
Completed
15
TMA
Providing and laying Street Light Complete Fitting
2000000
2000000
100%
Completed
16
32
Construction of RCC Slab Nallah near Raja Zahid House Baja line
700000
664216
100%
Completed
17
99
Construction of footpath M-Block U.C 99 near leads Factory
600000
590352
100%
Completed
18
98
Improvement of Chowk Ferdous Market to Service road Jinnah Bridge U.C 98
2200000
925000
60 %
W.I.P
19
99
Improvement of road near house No. 50 M-Block Gulberg III Lahore
432000
383569
100%
Completed
20
99
Construction of PCC Khan Colony Park U.C 99 Gulberg Lahore.
800000
797989
100%
Completed
21
128
Laying of Tuff Tiles D-Block Market Faisal Town U.C 128
550000
530949
100%
Completed
22
32
PCC remaining portion 60 Quarters U.C 32
1000000
998500
100%
Completed
23
32
Construction of PCC remaining portion Parachute Colony link Masjid Street to Robina Ejaz Street
1700000
1640262
100%
Completed
24
TMA
Supply of material patch work for mini asphalt plant
1147200
350000
40%
W.I.P
25
129
Improvement of road Q-Block Park to Darbar Baba Karian Wala Model Town extension
400000
397396
100%
Completed
26
31
PCC Street near Tube wall Achant Garh Remaining portion U.C 31
200000
200000
100%
Completed
27
128
PCC link Streets main bazar Muhammad Pura U.C 128
200000
199400
100%
Completed
28
97
Improvement of road parking near main building police station Gulberg
1000000
905457
100%
Completed
29
95
Improvement of road near main market Gulberg Lahore
600000
30%
W.I.P
30
95
Improvement and repair PCC road main market near iqbal book corner Gulberg Lahore
600000
587671
100%
Completed
31
TMA
Dewatering sets with accessories
245000
204330
100%
Completed
32
31
Restoration of road cut Singh Pura Mandi
1300000
1298301
100%
Completed
33
32
Restoration of road cut main Munawar Sultana Road
661242
659258
100%
Completed
34
95
Construction of road 28-E 1 Gulberg
1100000
889000
100%
Completed
35
31
Widening and construction Engine Shed road U.C 31
1000000
995887
100%
Completed
36
76
Construction of Burni road Ghari Shahu U.C 76
1250000
1248559
100%
Completed
37
31
Construction of street block 424 to 425 Azam Street Engine Shed U.C 31
700000
697900
100%
Completed
38
31
Improvement of road singh pura U.C 31
3000000
2974093
100%
Completed
39
32
Construction of road link Azeem Ground U.C 32
1500000
1495816
100%
Completed
40
76
Construction and repair of wall Graveyard U.C 76
500000
230000
100%
Completed
41
31
Construction and repair wall graveyard Achant Garh U.C 31
500000
319700
100%
Completed
42
76
Widening road near fountain Main bazar Ghari Shahu
700000
255000
100%
Completed
43
TMA
Proving and fixing sodium street lights 250 W for Gulberg town Lahore
4500000
4495319
100%
Completed
44
TMA
Providing and fixing Mercury Street light 125 W for Gulberg town Lahore
1785000
1385000
90%
W.I.P
45
98
Improvement of road plot no 47 to graveyard G Block Gulberg III
800000
717072
100%
Completed
46
128
Construction and repair main road faisal town Lahore
778000
776444
100%
Completed
47
95
Improvement of road near Agriculture office 214-A Sundar Das Road
500000
498750
100%
Completed
48
32
Construction of PCC Filtration Point infront of Street Waheed Colony U.C 32
282000
280860
100%
Completed
49
76
Construction of PCC Streets Attiya Rasheed Ahata Rahim Buksh and Iqbal High School Streets link Burni Road Allama Iqbal Road U.C 76
865000
864352
100%
Completed
50
76
Providing and laying sewerage line and construction of PCC flooring Nawan Ahata Ghari Shahu U.C 76
1000000
994310
100%
Completed
51
76
Construction of PCC flooring different Streets Railway Stadium Ghari Shahu U.C 76
800000
772013
100%
Completed
52
76
Improvement of Feroz Street Ghari Shahu U.C 76
800000
800000
100%
Completed
53
32
Construction Nala Post Office Sample Road U.C 32
100000
99785
100%
Completed
54
31
Construction Footpath Engine Shed remaining portion
200000
197820
100%
Completed
55
31
Construction road list road near Lal Masjid Chowk U.C 31
200000
199560
100%
Completed
56
95
Improvement of road Junior Model School Gulberg to 55 F Gulberg II
1000000
808000
90%
W.I.P
57
95
Improvement of Main Bazar Canal Park and link Streets
2700000
885000
60%
W.I.P
58
31
Supply and erection Sodium Light Jamilabad
225000
218615
100%
Completed
59
95
Improvement of Road Punjab Text book Board Block E II near Qaddafi Stadium Gulberg III
882000
881133
100%
Completed
60
95
Improvement of road near Tikoni Park Main Market Gulberg
1500000
 
20%
W.I.P
61
TMA
Making of Sign Boards etc
800000
 
10%
W.I.P
62
TMA
Patch Work PECO Road Kot Lakhpat
3900000
3900000
100%
Completed
63
95
Improvement of Rana Shaukat Mehmood Road Gulberg Lahore
4100000
3896637
100%
Completed
64
TMA
Supply and erection Sodium Light 250 Watt Complete Fitting for TMA Gulberg Town Lahore
4450000
3830000
90%
W.I.P
65
TMA
Construction of different streets TMA Gulberg Town Lahore
4000000
3776000
80%
W.I.P
66
TMA
Patch work roads TMA Gulberg Town Lahore
4700000
4679852
100%
Completed
67
99
Reconditioning of different streets Nawaz Sharif Colony U.C 99
2000000
2000000
100%
Completed
68
97
Construction of road Nabi Pura # 2 link graveyard and railway line U.C 97
2120000
1734000
80%
W.I.P
69
97
Tuff tiles street No. 21 Nabi Pura Lala General Store Wali U.C 97
1100000
 
10%
W.I.P
70
97
Improvement of road tanki Wali near 17-T T Block Gulberg Lahore U.C 97
1765000
 
10%
W.I.P
71
97
Improvement of road 5 C-I to 47 C-1 wali Block C-I Gulberg III Lahore U.C 97
2500000
2185000
100%
Completed
72
95
Improvement of street Qurban Line and Abadi U.C 95
1000000
 
10%
W.I.P
73
95
Providing and laying Tuff tiles along the road Ahata Bhasi Ram Canal park U.C 95
550000
 
20%
W.I.P
74
95
PCC Pavement for Improvement of berms Sikander Malhi road U.C 95
2200000
1830000
80%
W.I.P
75
98
PCC street No. 3-A Makkah Colony U.C 98
1500000
 
10%
W.I.P
76
98
PCC Street No. 6-A Makkah Colony U.C 98
1500000
 
10%
W.I.P
77
98
PCC Street No. 14-D Makkah Colony U.C 98
1000000
623000
50%
W.I.P
78
98
PCC Street No. 18-D Makkah Colony U.C 98
1000000
307000
50%
W.I.P
79
98
PCC Street Masjid Wali Itehad Colony U.C 98 
1500000
 
10%
W.I.P
80
99
PCC C A A Colony Gopal Nager U.C 99
500000
482427
100%
Completed
81
99
RCC M C primary School Bhabra Ferozpur road including stone U.C 99
300000
137000
60%
W.I.P
82
99
PCC Overseas foundation road side berms U.C 99
800000
784548
100%
Completed
83
129
PCC Saleem Complex wali Street Liaqatabad U.C 129
825000
816936
100%
Completed
84
129
PCC Officers Colony mohallah Bohader pura U.C 129  
400000
399192
100%
Completed
85
129
PCC Khan Colony and Kauser Colony link streets Liaqatabad U.C 129
900000
720000
100%
Completed
86
129
PCC Monshi Nammat Street Liaqatabad U.C 129
300000
272000
100%
Completed
87
129
Construction of Naiyan Wala chowk to Jahgra chowk Kot lakh pat U.C 129
450000
450000
100%
Completed
88
129
Construction carpet Govt. girls high school road Liaqatabad U.C 129
1400000
 
50%
W.I.P
89
129
PCC Masjid Street Bohar Colony No. 2 U.C 129
800000
800000
100%
Completed
90
129
PCC Salar road including link streets U.C 129
1200000
454000
100%
Completed
91
129
PCC Church Street Liaqatabad U.C 129
400000
399860
100%
Completed
92
130
PCC FGA School Road Modern Colony U.C 130
1500000
1438081
100%
Completed
93
130
PCC Nasrat road near Tube well X Block U.C 130
1000000
999674
100%
Completed
94
130
PCC Qilla abadi including link streets
1000000
1000000
100%
Completed
95
130
PCC Nadeem Park including link streets
900000
894627
100%
Completed
96
130
PCC Bohar Colony near Jamia Masjid
850000
832015
100%
Completed
97
130
PCC Streets Saint Fancies Colony
600000
599400
75%
W.I.P
98
130
PCC Streets Modern Colony
1000000
979723
100%
Completed
99
130
PCC streets Salamat pura
1200000
1168000
90%
W.I.P
100
130
PCC Petor Street
250000
250000
100%
Completed
101
130
Construction of PCC including Sewerage Devid Street
400000
397035
100%
Completed
102
130
Construction of PCC Franskin Street
200000
198135
100%
Completed
103
130
PCC Christen graveyard street Modren colony
150000
114000
80%
W.I.P
104
130
PCC Chaman Street Modern colony
2000000
1294000
80%
W.I.P
105
130
PCC Ghulam Rasool Street Nadeem Park Kot Lakhpat
300000
300000
100%
Completed
106
130
PCC Mughal street Nawab Colony Kot Lakhpat
200000
200000
100%
Completed
107
130
PCC Manzoor street Nadeem Park Kot Lakhpat
400000
364425
100%
Completed
108
130
PCC Hayyat Rasool Street Nadeem Park Kot Lakhpat
200000
179739
100%
Completed
109
130
PCC Butt street Kot Lakhpat
150000
149910
100%
Completed
110
130
PCC Hashim Street Karman Wala Colony Kot Lakhpat
120000
120000
100%
Completed
111
130
PCC Bhatti street Modern Colony Kot Lakhpat
300000
282553
100%
Completed
1112
130
PCC Prince Street Bohar Colony No. 1
300000
290933
100%
Completed
113
130
PCC Shabir Street Bohar Colony No. 1 U.C 130
170000
168071
100%
Completed
114
130
PCC Doctor Ejaz Street Modern Colony U.C 130
200000
199443
100%
Completed
115
131
Improvement of street Muhammadi Muhalla U.C 131
1500000
460000
100%
Completed
116
131
PCC Habib Bank Stret Quaid-e-Azam Park U.C 131
800000
800000
100%
Completed
117
131
PCC Butt Street Habib Home U.C 131
1200000
920000
100%
Completed
118
131
PCC Stone factory Satto Katla Drain U.C 131
1000000
 
40%
W.I.P
119
131
PCC Usmania Masjid Street Kashmeri Muhalla
900000
850858
100%
Completed
120
126
Supply and erection street light including foundation span and pole sodium light 250 Watts Parking Barkat Market
830000
 
20%
W.I.P
121
TMA
Supply of Street light Material for TMA Gulberg Town Lahore
1500000
 
20%
W.I.P
122
TMA
Supply and erection of Sodium street Light 250 Watts Complete fittings
4000000
3920000
90%
W.I.P
123
TMA
Supply Street light Complete fitting 40 Watt Tube light
2000000
1125000
50%
W.I.P
124
TMA
Purchase T&P Material for Street Light
50000
48548
100%
Completed
125
31
Improvement of Singh Pura road remaining portion
1200000
1186758
100%
Completed
126
31
PCC Hope Road remaining portion
700000
699759
100%
Completed
127
76
Construction of PCC Streets behind Iqbal High School
500000
497615
100%
Completed
128
130
PCC Shama Street Nadeem Park Kot Lakhpat
120000
120000
100%
Completed
129
131
Construction of road including sewerage Mian street U.C 131
2500000
1395000
100%
Completed
130
 
Purchase Suzuki Cultus
800000
694000
100%
Completed
131
 
Purchase Suzuki Pik Up
500000
347000
100%
Completed
 
 
Total
 
 
 
 
 
   